Wood-Washington-Wirt Interstate Planning Commission
Wood-Washington-Wirt Interstate Planning Commission
  • Home
  • Transportation
    • Bike/Ped Trail Maps
    • EV Charging Stations
    • Freight
    • GIS
    • Mid-Ohio Valley Airport
    • Obligated Projects
    • Statewide ITS Plans
    • Transit
  • Planning Documents
    • Air Quality Conformity
    • Horizon 2045 LRTP
    • Horizon 2050 LRTP Info
    • Performance Measures
    • Progress Reports
    • 2024-2027 TIP
    • Draft 2026-2029 TIP
    • Unified Work Program
  • Plans & Studies
    • Bike/Ped
    • Environ. Overview Study
    • OH Traffic Counts
    • WV Traffic Counts
    • Traffic Studies
  • Funding Opportunities
    • Funding Overview
  • Title VI/EJ
    • Title VI
  • About WWW
    • By-Laws
    • Contact Us
    • Document Archive
    • Overview
    • Policy Board
    • Prospectus
    • Public Notices
    • Public Participation Plan
    • Staff
    • Technical Advisory Comm.
    • Travel Policy
  • More
    • Home
    • Transportation
      • Bike/Ped Trail Maps
      • EV Charging Stations
      • Freight
      • GIS
      • Mid-Ohio Valley Airport
      • Obligated Projects
      • Statewide ITS Plans
      • Transit
    • Planning Documents
      • Air Quality Conformity
      • Horizon 2045 LRTP
      • Horizon 2050 LRTP Info
      • Performance Measures
      • Progress Reports
      • 2024-2027 TIP
      • Draft 2026-2029 TIP
      • Unified Work Program
    • Plans & Studies
      • Bike/Ped
      • Environ. Overview Study
      • OH Traffic Counts
      • WV Traffic Counts
      • Traffic Studies
    • Funding Opportunities
      • Funding Overview
    • Title VI/EJ
      • Title VI
    • About WWW
      • By-Laws
      • Contact Us
      • Document Archive
      • Overview
      • Policy Board
      • Prospectus
      • Public Notices
      • Public Participation Plan
      • Staff
      • Technical Advisory Comm.
      • Travel Policy
  • Home
  • Transportation
    • Bike/Ped Trail Maps
    • EV Charging Stations
    • Freight
    • GIS
    • Mid-Ohio Valley Airport
    • Obligated Projects
    • Statewide ITS Plans
    • Transit
  • Planning Documents
    • Air Quality Conformity
    • Horizon 2045 LRTP
    • Horizon 2050 LRTP Info
    • Performance Measures
    • Progress Reports
    • 2024-2027 TIP
    • Draft 2026-2029 TIP
    • Unified Work Program
  • Plans & Studies
    • Bike/Ped
    • Environ. Overview Study
    • OH Traffic Counts
    • WV Traffic Counts
    • Traffic Studies
  • Funding Opportunities
    • Funding Overview
  • Title VI/EJ
    • Title VI
  • About WWW
    • By-Laws
    • Contact Us
    • Document Archive
    • Overview
    • Policy Board
    • Prospectus
    • Public Notices
    • Public Participation Plan
    • Staff
    • Technical Advisory Comm.
    • Travel Policy

Fiscal Year 2021-2024 Biennial Transportation Improvement Program

The Transportation Improvement Program (TIP) includes projects consistent with the goals identified in the Wood-Washington-Wirt Interstate Planning Commission Horion 2045: Long Range Transportation Plan.

2021-2024 Transportation Improvement Program (TIP)

2021-2024 TIP Projects Dashboard for Wood County, West Virginia

2021-2024 TIP Projects Dashboard for Wood County, West Virginia

WWW FY 2021-2024 Biennial Transportation Improvement Program cover page

Click on the image above, or click here, to view the PDF of the 2021-2024 Transportation Improvement Program (TIP).

Amended

June 14, 2023

Administrative Adjustments

May 16, 2023

2021-2024 TIP Projects Dashboard for Wood County, West Virginia

2021-2024 TIP Projects Dashboard for Wood County, West Virginia

2021-2024 TIP Projects Dashboard for Wood County, West Virginia

WWW FY 2021-2024 WV TIP projects map with costs and funding details

Click on the image above, or click here,  to view the 2021-2024 TIP Projects Dashboard for Wood County, West Virginia. 

2021-2024 TIP Projects Dashboard for Washington County, Ohio

2021-2024 TIP Projects Dashboard for Wood County, West Virginia

2021-2024 TIP Projects Dashboard for Washington County, Ohio

WWW FY 2021-2024 OH TIP projects map with costs and funding details

Click on the image above, or click here,  to view the 2021-2024 TIP Projects Dashboard for the seven townships in Washington County, Ohio that are in the WWW Study Area. 

2021-2024 TIP Amendments

June 14, 2023

Wood County Amendments


Project #: S354-77-169.68 (STBG-0077(11 S)D) 

Project Description: Mineral Wells-US 50 - Mill and resurface with overlay and guardrail
Schedule: Construction - FY 23
Total Project Cost: $20,800,000
Amendment: Project added


Project #: S35468170700 (NHPP0068 l 92D)

Project Description: Sen JF Deem Mem Br - WV 68 - Senator JF Deem Memorial Bridge - 0.30 miles north of US 50. Rehab piers, replace expansion joints, seal and patch.
Schedule: Construction - FY 25
Total Project Cost: $18,500,000
Amendment: Total project cost increased from $15,000,000 to $18,500,000.

March 15, 2023

Washington County Amendments


Project #: PID 111436 (WAS SR 26 0.160 Acme St) 

Project Description: Minor rehab on WAS 26 0.16-0.63. Acme Street in Marietta. PE includes bicycle and pedestrian needs assessment.
Schedule: Construction - FY 24
Total Project Cost: Construction - $957,000
Amendment: Construction changed from FY24 to FY26 and will be included in the FY24-27 TIP. Construction phase removed from FY21-24 TIP.


Project #: PID 118729 (WAS CR 79 0.00) 

Project Description: Two-lane resurfacing project on WAS CR 79 0.00-5.654. Begin at CR 4.
Schedule: Construction - FY 24
Total Project Cost: Construction - $1,054,255
Amendment: Project added for construction in FY24. Local funds for CON are $474,728 and MPO STBG funds for CON are $579,528 for a total project cost of $1,054,255. 


Wood County Amendments


Project #: S354-68-17.07 00 (NHPP-0068(187)D) 

Project Description: WV 68 - Senator JF Deem Memorial Bridge.
Schedule: Construction - FY 25
Total Project Cost: $12,000,000
Amendment: Construction changed from FY23 to FY25 and will be included in the FY24-27 TIP. Construction phase removed from FY21- 24 TIP. 

September 24, 2022

Washington County Amendments


Project #: PID 117555 (WAS-Walking Trail Slip Repair)

Project Description: Marietta – Slip repair on the Marietta River Trail.
Schedule: Construction – FY 23
Total Project Cost: Construction - $1,250,000
Amendment: Project added

August 31, 2022

Wood County Amendments


Project #: U354-002-023 l l .08 NHPP-2022(057)D 

Project Description: WV 2 - Parkersburg-St. Mary's Mitigation

Schedule: Construction FY 22

Total Project Cost: $172,000 

Amendment: Project added.


Project #: U354-14-10.43 00 STP-0014(174)D 

Project Description: 26th A venue - Blizzard Drive. Widen, add lanes.

Schedule: ght-of-Way FY 22 

Total Project Cost: $4,000,000

Amendment: Project added. 

May 25, 2022

Wood County Amendments


Project #: MOVTA Section 5339 

Project Description: Purchase 8 replacement bus shelters. 

Schedule: FY22

Total Project Cost: $46,302

Amendment: Project added. FTA share $37,041.00. Local share $9,261.00. 


Project #: MOVTA Section 5339 

Project Description: Purchase a generator for the maintenance facility. 

Schedule: FY22

Total Project Cost: $73,871

Amendment: Project added. FTA share $59,096.00. Local share $14,775.


Project #: MOVTA Section 5339 

Project Description: Security lighting at terminal. 

Schedule: FY22

Total Project Cost: $11,259

Amendment: Project added. FTA share $9,007.00. Local share $2,252.00. 

November 10, 2021

Wood County Amendments


Project #: U354-2-27.56 00 HSIP-0002(569)D HSIP-0002(570)DTC

Project Description: WV 2 - Addition of a Left turn lane at Corbitt Hill Road.

Schedule: ROW FY 22 (Authorization: 08/31/2021)  Construction FY 22

Total Project Cost: $1,337,000

Amendment: Project deleted from WV Non-Groupable Project list and moved  to the WV Grouped Project List.


Project #: U354-1416/1.51 HSIP-1416(002)DTC 

Project Description: Rosemar Road (CO 14/16) Construct Left turn lane at Twin  Lakes Road and Jackson Park.

Schedule: Construction FY 22

Total Project Cost: $1,000,000

Amendment: Project deleted from WV Non-Groupable Project list and moved to the WV Grouped Project List. Construction moved from FY 21 to FY 22.

Washington County Amendments


Project #: PID 110275 (WAS-Marietta-Signals (Phase 3)
Project Description: Marietta – Construction of ADA compliant curb ramps and new traffic   signal cabinet equipment and signal heads.    WAS-7-21.86-22.20, WAS-60-0.80-1.14 (Phase 3).
Schedule: Construction – FY 23
Total Project Cost: $686,391
Amendment: Project deleted


Project #: PID 110274 (WAS-Marietta-Signals (Phase 2))
Project Description: Marietta – Construction of traffic signals and fiber optic interconnecting system. WAS-7-21.86-22.20, WAS-60-0.80-1.14. (Phase 2).
Schedule: Construction – FY 23
Total Project Cost: $686,391
Amendment: Project Fiscal Year revised from FY 22 to FY 23. Cost increased from $282,874 to $686,391. Project scope was revised to merge Phase 3 with Phase 2.


Project #: PID 111436 (WAS-SR26-0.016)
Project Description: Minor rehab on WAS 26 0.16-0.63. Acme Street in the City of   Marietta.  PE includes bicycle and   pedestrian needs assessment.
Schedule: Preliminary Engineering and Construction - FY 24
Total Project Cost: Preliminary Engineering - $91,000, Construction - $957,000
Amendment: Project moved from Statewide Line Item list and modified to include MPO CMAQ funding in FY 24. Preliminary Engineering phase added in FY 24. Construction phase moved from FY 23 to FY 24. Cost increased from $957,000 to $1,048,000


Wood County Amendments


Project #: S354-77-176.32 00 (NHPP-0773(495)D)
Project Description: Bridge replacement project on I-77 at US 50 Interchange (north and south).
Schedule: Construction - Fiscal Year 2025
Total Project Cost: $14,800,000
Amendment: Construction phase scheduled in Fiscal Year 2024 is being moved from the current FY 2021-2024 TIP period and into Fiscal Year 2025.


Wood County Amendments


Project #: U354-14-10.43 00 (STP-0014(174)D)
Project Description: Widen WV 14 to provide additional lanes from 26th Street to Blizzard Drive in Parkersburg.
Schedule: Engineering - Fiscal Year 2021
Total Project Cost: $670,000
Amendment: New Project


Project #: U354-2-27.56 00 (HSIP-0002(569)D)
Project Description: WV 2 – Addition of left turn lane at Corbitt Hill Road.
Schedule: Right-of-Way and Construction - Fiscal Year 2021
Total Project Cost: $1,160,000
Amendment: New Project


Project #: S354-77-176.32 00 (NHPP-0773(495)D)
Project Description: Bridge replacement project on I-77 at US 50 Interchange (north and south).
Schedule: Engineering and Right-of-Way – Fiscal Year 2023
                 Construction – Fiscal Year 2024
Total Project Cost: $14,800,000
Amendment: New Project


Project #: U354-14/16-1.51 (HSIP-1416(001)D)
Project Description: Rosemar Road (CO 14/16) Construct left turn lane at mile post 1.91 (Twin Lakes Road) and mile post 2.21 (Woodland Park Drive).
Schedule: Construction – Fiscal Year 2021
Total Project Cost: $1,000,000
Amendment: New Project


Project #: S354-68-17.07 00 (NHPP-0068(184)D)
Project Description: WV 68 – Senator JF Deem Memorial Bridge - 0.30 miles north of US 50. Rehab piers, replace expansion Joints, seal and patch.
Schedule: Engineering and Right-of-Way – Fiscal Year 2022
                 Construction – Fiscal Year 2024
Total Project Cost: $17,250,000
Amendment: New Project


WWW Interstate Planning Commission (WWW)

709 Market Street, Parkersburg, West Virginia 26101

304.422.4993

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept